REMOVAL
CAUTION / NOTICE / HINT
The necessary procedures (adjustment, calibration, initialization or registration) that must be performed after parts are removed and installed, or replaced during park/neutral position switch assembly removal/installation are shown below.
Necessary Procedures After Parts Removed/Installed/Replaced| Replacement Part or Performed Procedure | Necessary Procedure | Effect/Inoperative Function when Necessary Procedure not Performed | Link |
|---|---|---|---|
|
*1: When performing learning using the Techstream.
Click here | |||
| Battery terminal is disconnected/reconnected | Memorize steering angle neutral point | Lane Control System | |
| Pre-collision System | |||
| Intelligent Clearance Sonar System*1 | |||
| Lighting System (w/ Automatic Headlight Beam Level Control System) | | ||
| Parking Assist Monitor System | | ||
| Panoramic View Monitor System | | ||
| Initialize back door lock | Power Door Lock Control System | | |
| Reset back door close position | Power Back Door System (w/ Outside Door Control Switch) | | |
PROCEDURE
1. PRECAUTION
NOTICE:
After turning the engine switch off, waiting time may be required before disconnecting the cable from the negative (-) battery terminal. Therefore, make sure to read the disconnecting the cable from the negative (-) battery terminal notices before proceeding with work.
Click here
2. SECURE VEHICLE
(a) Fully apply the parking brake and chock a wheel.
CAUTION:
3. REMOVE COOL AIR INTAKE DUCT SEAL
Click here
4. REMOVE INLET AIR CLEANER ASSEMBLY
Click here
5. DISCONNECT CABLE FROM NEGATIVE BATTERY TERMINAL
NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected.
Click here
6. REMOVE BATTERY
| (a) Disengage the 2 claws to open the battery terminal cap. |
|
(b) Loosen the nut and disconnect the cable from the positive (+) battery terminal.
| (c) Remove the bolt, nut and battery clamp sub-assembly. |
|
(d) Remove the battery insulator.
(e) Remove the battery and battery tray.
| (f) Remove the battery clamp bolt from the battery carrier sub-assembly. |
|
7. DISCONNECT TRANSMISSION CONTROL CABLE ASSEMBLY
(a) Move the shift lever to N.
| (b) Remove the nut and disconnect the transmission control cable assembly from the transmission control shaft lever. |
|
8. REMOVE PARK/NEUTRAL POSITION SWITCH ASSEMBLY
| (a) Disconnect the park/neutral position switch assembly connector. |
|
(b) Remove the nut and transmission control shaft lever from the manual valve lever shaft sub-assembly.
| (c) Using a screwdriver, bend back the tabs of the lock plate and remove the lock nut and lock plate from the park/neutral position switch assembly. |
|
| (d) Remove the 2 bolts and park/neutral position switch assembly from the automatic transaxle case sub-assembly. NOTICE: Before removing the park/neutral position switch assembly, remove any dirt or rust on the installation portion of the manual valve lever shaft sub-assembly. Be sure to remove the park/neutral position switch assembly straight along the manual valve lever shaft sub-assembly while being careful not to deform the plate spring that supports the manual valve lever shaft sub-assembly. If the plate spring is deformed, the park/neutral position switch assembly cannot be reinstalled correctly. |
|
On-vehicle Inspection
InspectionLexus RX (RX 350L, RX450h) 2016-2026 Repair Manual > Sfi System: HO2S Heater Control Circuit Bank 1 Sensor 2 Circuit Short to Battery (P003612,P003614,P005612,P005614,P014118,P016118,P102A9E,P105A9E)
DESCRIPTION Refer to DTC P013611. Click here HINT:
When any of these DTCs are stored, the ECM enters fail-safe mode. The ECM turns off the heated oxygen sensor heater in fail-safe mode. Fail-safe mode continues until the engine switch is turned off.
The heated oxygen sensor heater circuit us ...
Lexus RX (RX 350L, RX450h) 2016-2026 Repair Manual > Fuel Injector (for Port Injection): Installation
INSTALLATION PROCEDURE 1. INSTALL FUEL INJECTOR ASSEMBLY HINT: Perform "Inspection After Repair" after replacing a fuel injector assembly. Click here (a) Apply a light coat of spindle oil or gasoline to 6 new O-rings, and install 1 to each fuel injector assembly. NOTICE: Check that there is no da ...