Lexus RX (RX 350L, RX450h) 2016-2025 Repair Manual: Inspection

INSPECTION

PROCEDURE

1. INSPECT SEMICONDUCTOR POWER INTEGRATION ECU

(a) IG2 RELAY:

(1) Measure the resistance according to the value(s) in the table below.

Standard Resistance:

Tester Connection

Condition

Specified Condition

B-1 - 1F-4

Battery voltage not applied between terminals 1E-1 and 1D-14

10 kΩ or higher

B-1 - 1G-3

B-1 - 1G-4

B-1 - 1F-4

Battery positive (+) → 1E-1

Battery negative (-) → 1D-14

Below 1 Ω

B-1 - 1G-3

B-1 - 1G-4

If the result is not as specified, replace the semiconductor power integration ECU.

*a

Component without harness connected

(Semiconductor Power Integration ECU)

(b) EFI-MAIN RELAY:

(1) Measure the resistance according to the value(s) in the table below.

Standard Resistance:

Tester Connection

Condition

Specified Condition

B-1 - 1G-1

Battery voltage not applied between terminals 1G-6 and 1D-14

10 kΩ or higher

B-1 - 1G-2

B-1 - 1G-7

B-1 - 1G-8

1F-2 - 1G-1

B-1 - 1G-1

Battery positive (+) → 1G-6

Battery negative (-) → 1D-14

Below 1 Ω

B-1 - 1G-2

B-1 - 1G-7

B-1 - 1G-8

1F-2 - 1G-1

If the result is not as specified, replace the semiconductor power integration ECU.

*a

Component without harness connected

(Semiconductor Power Integration ECU)

(c) A/F RELAY:

(1) Measure the resistance according to the value(s) in the table below.

Standard Resistance:

Tester Connection

Condition

Specified Condition

B-1 - 1F-1

Battery voltage not applied between terminals 1G-1 and 1D-14

10 kΩ or higher

B-1 - 1F-1

Battery positive (+) → 1G-1

Battery negative (-) → 1D-14

Below 1 Ω

If the result is not as specified, replace the semiconductor power integration ECU.

*a

Component without harness connected

(Semiconductor Power Integration ECU)

(d) H-LP RH-LO RELAY:

(1) Measure the resistance according to the value(s) in the table below.

Standard Resistance:

Tester Connection

Condition

Specified Condition

B-1 - 1E-2

Battery voltage not applied between terminals B-1 and 1D-8

10 kΩ or higher

*a

Component without harness connected

(Semiconductor Power Integration ECU)

(2) Measure the voltage according to the value(s) in the table below.

Standard Voltage:

Tester Connection

Condition

Specified Condition

1E-2 - Battery negative (-)

Battery positive (+) → B-1

Battery negative (-) → 1D-8

11 to 14 V

If the result is not as specified, replace the semiconductor power integration ECU.

(e) H-LP LH-LO RELAY:

(1) Measure the resistance according to the value(s) in the table below.

Standard Resistance:

Tester Connection

Condition

Specified Condition

B-1 - 1E-3

Battery voltage not applied between terminals B-1 and 1D-8

10 kΩ or higher

*a

Component without harness connected

(Semiconductor Power Integration ECU)

(2) Measure the voltage according to the value(s) in the table below.

Standard Voltage:

Tester Connection

Condition

Specified Condition

1E-3 - Battery negative (-)

Battery positive (+) → B-1

Battery negative (-) → 1D-8

11 to 14 V

If the result is not as specified, replace the semiconductor power integration ECU.

(f) Semiconductor power integration ECU ground:

(1) Measure the resistance according to the value(s) in the table below.

Standard Resistance:

Tester Connection

Condition

Specified Condition

1D-14 - 1G-5

Always

Below 1 Ω

If the result is not as specified, replace the semiconductor power integration ECU.

*a

Component without harness connected

(Semiconductor Power Integration ECU)

    Removal
    REMOVAL CAUTION / NOTICE / HINT The necessary procedures (adjustment, calibration, initialization, or registration) that must be performed after parts are removed and installed, or replaced during int ...

    Installation
    INSTALLATION PROCEDURE 1. INSTALL SEMICONDUCTOR POWER INTEGRATION ECU (a) Connect the 5 connectors. (b) Engage the 2 claws to install the semiconductor power integration ECU as shown in the illustrati ...

    Other materials:

    Lexus RX (RX 350L, RX450h) 2016-2025 Repair Manual > Charging System: Charging Failure
    PROCEDURE 1. CHECK GENERATOR PULLEY WITH CLUTCH (ON-VEHICLE INSPECTION) (a) Start the engine and visually check that the generator rotor assembly (fan) in the generator assembly is operating. OK: The generator rotor assembly (fan) is operating. NG REPLACE GENERATOR PULLEY WITH CLUTC ...

    Lexus RX (RX 350L, RX450h) 2016-2025 Owners Manual > Basic operation of the Remote Touch screen: 12.3-inch display
    12.3-inch display overview ■ Full screen display The following functions can be displayed full screen: Initial screen "Menu" screen Map screen* *: Refer to the "NAVIGATION SYSTEM OWNER'S MANUAL". ■ Split-screen display Different information can be displayed on the left and right ...

    Lexus RX (RX 350L, RX450h) 2016-{YEAR} Owners Manual

    Lexus RX (RX 350L, RX450h) 2016-{YEAR} Repair Manual

    © 2025 Copyright www.lexusrx.net
    0.0138